Step 1: Understanding the meaning of DPR.
The term DPR stands for Detailed Project Report.
It is an essential document prepared before the execution of any large-scale project.
The DPR provides an in-depth analysis and detailed description of all aspects of a project — including its objectives, background, financial requirements, feasibility, and technical details.
In simple terms, it acts as a roadmap or master plan that guides the implementation of the project from start to finish.
Step 2: Components of a DPR.
A standard DPR usually includes the following key sections:
- Project background and justification
- Objectives and scope of the project
- Technical specifications and design details
- Cost estimates and financing plan
- Implementation schedule and monitoring mechanism
- Risk assessment and mitigation measures
All of these sections are interlinked and designed to ensure that every stage of the project is properly executed.
Step 3: Why it is an Implementation Plan.
Since a DPR provides detailed guidelines on how the project should be executed, it is primarily an Implementation Plan.
It goes beyond being just a proposal or working plan; it sets out the operational framework for the actual execution of the project on the ground.
It outlines the activities, resources, manpower, and timelines necessary for successful completion.
Step 4: Analysis of Options.
- (1) Working plan: A working plan may refer to an internal short-term document, not a detailed guide for entire project execution.
- (2) Action plan: Although DPR includes actions, it is broader and more detailed than a mere action plan.
- (3) Implementation plan: Correct — because the DPR is intended to provide all necessary details to implement the project.
- (4) None of these: Incorrect, as the DPR clearly fits the description of an implementation plan.
Step 5: Conclusion.
Hence, the Detailed Project Report (DPR) is best described as an Implementation Plan.