Question:

Cloth Makers Inc. has p spindles, each of which can produce q metres of cloth on an average in r minutes. If the spindles are made to run with no interruption, then how many hours will it take for 20,000 meters of cloth to be produced?

Updated On: Oct 3, 2024
  • 20000 (pq)/r
  • 20000 (q)/p
  • 20000 (pr)/(pq)
  • 20000 r/60 (pq)
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Time taken to make \((pq)\) metres of cloth = \(r\) min
Time taken to make 20,000 m of cloth = \(\frac{r}{pq} \times 20,00,000\) mintues
Therefore, Required time (in hour) =\(20,00,00  \times 60(\frac{r}{pq})\)
The correct answer is (D) : 20000 r/60 (pq)