A typical control chart has two control limits: the upper control limit (UCL) and the lower control limit (LCL). These limits help in monitoring the process variations and maintaining quality control.
Step 2: Analyzing the options.
(A) 2: Correct. A control chart has two control limits – UCL and LCL.
(B) 1: Incorrect. A control chart needs both upper and lower limits to function effectively.
(C) 4: Incorrect. Control charts typically have only two limits.
(D) 5: Incorrect. Control charts do not typically require five control limits.
Step 3: Conclusion.
The correct answer is (A) 2, as control charts have two control limits: upper and lower.
Final Answer:} 2.