Question:

A water resources project with an expected life of 25 years has to be designed for an acceptable risk of 5% against a design flood. The return period for the design flood (in years) is ........... (rounded off to the nearest integer).

Show Hint

When calculating the return period, ensure that the risk and expected life are correctly substituted into the formula. The return period is the inverse of the probability of exceedance.
Updated On: Apr 3, 2025
  • 488
  • 485
  • 490
  • 495
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The return period \( T \) is calculated using the formula: \[ {Risk} = 1 - \left(1 - \frac{1}{T}\right)^n, \] where:
- \( n = 25 \) years (the expected life of the project),
- Risk = 5%.
Substituting the values into the formula:
\[ 0.05 = 1 - \left(1 - \frac{1}{T}\right)^{25}. \] Solving for \( T \), we get: \[ T = \frac{1}{1 - (0.95)^{1/25}} \approx 488 \, {days}. \] Thus, the return period is approximately 488 days, which corresponds to option (A).
Was this answer helpful?
0
0

Questions Asked in GATE CE exam

View More Questions