Question:

A factory is to commission two production lines. Production line 1 is to use existing technology. Production line 2 is to use the latest innovation in technology and, while promising to achieve considerable advances in productivity, it will take longer to start and is likely to experience teething problems. Graph indicates the productive record of each product line. Refer to the graph to answer the following.
 Production line 1 is to use existing technology. Production line 2 is to use the latest innovation in technology
A. Can the duration of reported breakdown be established?
B. Can the loss of production be quantified?

Updated On: Jul 29, 2024
  • Both questions A and B can be answered
  • Only A question can be answered
  • Only B question can be answered
  • Neither question can be answered
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is (B) :Only A question can be answered.
Was this answer helpful?
0
0