Question:

A contractor employed a certain number of workers to complete a project in 100 days. However, after 25 days, he found that only one-third of the work had been completed. How many additional workers must he employ so that the project can be completed on time?

Show Hint

In work and time problems, always compare expected progress with actual progress. If actual work>expected, no extra workers are required; if actual<expected, calculate shortfall and proportionally add more workers.
Updated On: Aug 25, 2025
  • 25
  • 30
  • 35
  • 40
  • None of the above
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: Represent total work.
Let the total work required for the project be equal to 1 unit (100%).
The work must be completed in 100 days.
Step 2: Work done in first 25 days.
It is given that only one-third of the work has been completed in 25 days.
So, work completed = \( \tfrac{1}{3} \).
Work remaining = \( 1 - \tfrac{1}{3} = \tfrac{2}{3} \).
Step 3: Determine actual capacity of existing workers.
If in 25 days, the workers can do one-third of the work, then in 100 days, they would have completed \[ \frac{100}{25} \times \frac{1}{3} = 4 \times \frac{1}{3} = \frac{4}{3}>1 \] Wait: Let’s carefully recalculate.
- In 25 days → work done = 1/3.
- So, in 1 day → work done = 1/75.
- In 100 days → total work possible = 100 × (1/75) = 4/3.
This shows the workers’ capacity is to finish the job in less than 100 days if they continue. But we must double-check.
Step 4: Re-examine the requirement.
Work done in 25 days = 1/3.
Work remaining = 2/3.
Time remaining = 100 − 25 = 75 days.
If the same workforce continues, in 75 days, they would complete
= (75/25) × (1/3) = 3 × (1/3) = 1.
That means they will finish exactly on time.
So there is no need for extra workers.
But wait — let us verify with the intended question logic. Sometimes such questions assume "less than expected progress" and ask for extra manpower.
Step 5: Adjust interpretation.
Expected work in 25 days = 25% of project.
Actual work done = 33.33%.
Since more work is completed than expected, no additional workers are required.
Hence, the correct answer is "None of the above".
Step 6: Conclude.
The project can be completed on time with the existing workforce. No extra workers are required. \[ \boxed{\text{None of the above (Option E)}} \]
Was this answer helpful?
0
0

Questions Asked in XAT exam

View More Questions