Question:

A can do a piece of work in 24 days. If B is 60 % more efficient than A, then the number of days required by B to complete the work:

Updated On: Oct 16, 2024
  • 10
  • 15
  • 12
  • 9.6
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is (B):15