Question:

A can complete a task in 6 days, B can complete it in 8 days, and C can complete it in 12 days. If they all work together, how many days will be required to complete the task?

Updated On: Oct 15, 2024
  • 5 days approx
  • 2 days approx
  • 4 days approx
  • 3 days approx
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

The correct option is (D): 3 days approx